Hi
I am using jira 6.1.3 and i have a problem
My developers backdate the time spent on a task but that is not reflected in t he burndown chart and the Time Spent chart.
If i did log time for that day on the correct day, then it registers as Work logged but if I backdated it, it will register and Scope change.
Anyone have issues?