I am looking to move our 9.4 SERVER Jira from Oracle 12c to 19c on Windows. The actual Jira release doesn't matter as the steps will be the same for any, but just want to check.
Presumably, in simple terms this is accomplished as follows:
1) Create new 19c database for Jira to live in and start it up.
2) Export Jira data from within current 12c Jira. Attachments and nothing else changing in the directories for Atlassian.
3) Point existing Jira to new Oracle database via …\Atlassian\JIRA\bin\config.bat
4) Shutdown/startup Jira? – not sure on this bit
When I log into Jira, I would expect it to have no issues once linked to new DB
5) Import Jira data from above so now good to go (it will pick up the Attachments as before),
Have I missed anything?