In my team I bulk update tasks into Jira. An Epic may contain anything between 50 to 1000 tasks. We set the start date of a task to the first day of month and end date to last day of month. The start and end date of tasks is governed by the project schedule. Projects may run for a few months or a few years. During the course of the projects some tasks may delay which means we have to update the start and end date of those tasks plus the tasks that are due in the following months.
My question is, is there a way of auto updating the proceeding tasks? Do I have to link the tasks or set precedence and how? Appreciate your help.