Overview
During grooming of sprint X, stories that require automation development are marked with a custom field that determine if an automation task needs to be created or not. Tasks that are created during this process will be developed on sprint X+1.
Problem
When trying to define a rule to move created task to sprint X+1, Jira only allows me to select 'next sprint', however 'Next sprint' is actually sprint X according to Jira as it adjacent to the active sprint.
Sprint X is a future sprint and the task is eventually not moved because Jira finds that it is it already in 'Next sprint'...
Is there a way to acheive this without having to specify to which sprint the task is intended for?