Good day,
I am trying to set up the advanced roadmaps feature to auto adjust the start and end dates of tasks/ stories based on dependencies. For example if Task 1 is delayed for three days than it was planned for (i.e. we extended the due date), the subsequent Task 2, which is blocked by task 1, keeps the same start date and does not change. I would like to find a way to automate this, but unfortunately we do not have the automation plugin for now, which I know may be able to solve this issue.
Jira Server v8.20.6
Thanks!