Hi Community,
i am trying to make one business scenario in Structure and for that I use effectors in Structure but there is a problem.
The project ticket should be the sum of all work package
Σ Original Estimate
- Project-1 6w
- Workpackage-1 1w
- Workpackage-2 2w
- Workpackage-3 3w
In any case, the effector sets the values, but it is wrong.
For 6w as in the example above effector is getting 1w 4d somehow.
Do anyone know why and how to correct this?
The formula i use:
and this one doesnt work to:
WITH ProjectEstimate = SUM#children { IF(IssueType = "Work Package"; OriginalEstimate) } :
JIRA_DURATION(CONCAT(ProjectEstimate / 3600 / 1000; "h"))
and assignment is made via the effector to the jira field OriginalEstimate.
Best regards