Hi @Sofia E Lizarraga , welcome to the Atlassian Community!
When you click on View settings, do you have the option Progress under More details enabled?
Hi Dave, thanks for answering my questions, yes is enable , I took a screenshoot of the checkmark enable
That was a wrong answer from me anyway.
The progress bar of the child issues are shown when an issue is added to an active sprint of a scrum board and determined by the start and end date of the sprint. You cannot change this for the standard issue types.
They progress bar of the child issues is not available for kanban board.