I am estimating in story points and time tracking in hours. I want the remaining hours field in the user story to be the total of the remaining hours in the sub-tasks. But I cannot enter sub-task remaining hours in Plan mode, only in Work mode. The user story is not available in Work mode until I start the sprint. But if I start the sprint without remaining hours in the user stories, the ideal burn-down chart is not plotted.
It's a Catch-22 situation. The only way I can get the initial burn-down plotted is to put guesswork hours remaining nto the user stories, whereas they should be the sum of the sub-task hours remaining. But I can't enter the sub-tasks hours remaining until I've started the sprint.
Surely I should be able to enter sub-task hours remaining in Plan mode?
Jira 5.2.5 Greenhopper 6.1.2