Hey,
I am trying to create issues from CSV with original estimate time included. (See picture 1 below)
We are using 37h/Week which is 7.4Hrs/Day.
Column Original Estimate in Sec is mapped to Original Estimate (See picture 2).
Result is not ok (See Picture 3).
For Subtask 1 : result = 1d 3h 36 min (=39600 sec) which should be 1d 3h 42 min
For Subtask 2 : result = 2w (=266400 sec) which is ok
For Subtask 3 : result = 7h (=25200 sec) which should be 1d,
I think the cause is the loss of decimals
- 39960/3600 = 11,1 --> 11/7.4 = 1d 3h 36 min (=39600 sec)
- 266400/3600 = 74 --> 74/7.4 = 2w (=266400 sec)
- 26640/3600 = 7,4 --> 7/7.4 = 7h (=25200 sec),
Can anyone help ?
Pic 1

Pic 2 
Pic 3