Hello everyone, thank you for your time in addressing my problem
My problem is this: I use the add-on to Jira called BIG PICTURE, it allows me to link my Gantt charts to the tasks that are given to my teams
I create a task that has a planned duration of 4 days.
My collaborator works on it for 2 days and finishes the task earlier than expected.
So there are 2 days of work left in Jira's memory, but 0 in real life.
My teammate updates the remaining time from 2 days to 0 minutes.
Following this manipulation BIG PICTURE adds 1 day of remaining time
How do I get BIG PICTURE not to change my times ?