Hi, Is it possible to do a Sprint Burndown chart that is based on tasks rather than story points ? And specifically hours on those task's original estimates rather than Story Points for the parent Story ? Regards Michael
Yes you can! If you have the correct permission, go the "Board > Configuration > Columns > Estimation" then choose what setting do you likeĀ