Hello,
we use WBS Gantt to import MS Project plans. When importing issues, the fields original estimate and remaining estimate are automatically populated. I assume this happens based on the duration which is specified in the plan.
Is it possible to configure WBS Gantt to not populate those fields? Estimates based on the duration are wrong in our case because the plan contains the duration during which a task has to be completed, not the estimate how long a task will take. We want to estimate each task individually after it has been imported.
Thanks in advance!