Hello,
If I "Move" a JIRA ticket from a task to a story, what will happen to the sub-tasks of that task? Will they become sub-tasks of the Story?
Thank you
Hi @Noam Guttman,
Yes, they will just remain as sub-tasks of the story.
Thanks! @Walter Buggenhout
Hi, how can I convert a Task to a Story please?
Disregard, discovered how to do it. Thanks.
@Rubie Guerrero how did you change the task to a story?
Horrible UI design - no one would figure out (other than the developer of this so called feature) that this is how it's done.
Shankar
There are two ways this can be achieved
1)By clicking on the Epic, Story, Task, Sub task,bug, it will show the of change issue type and select the type and it get converted immediately.
2) ... on the right corner and click on move option, then select type and continue until the last step.