I am having a play with time tracking and using it for work estimates. so far so good apart from the fact that if a task records remaining time estimate as 0h i.e. task is done , in the resourcing pane i can see that the hours are still being counted.

When i checked my config and i turned on set task as milestone when duration / estimate is set to ) the hour calculation in resource pane seems to work fine.

My question is can I have tasks that have remaining time 0h show as task bars in gantt and have resource pane not take into account the hours as they are zero ?