Hi, In my Gantt tracker, I want to see what the expected finish date is, based on auto scheduling of tasks (based on estimated time and dependencies). I checked multiple fields - due date, end date, finish date, but none of them show the information. What field should I use for this?
See image below, where I tried using due date, but seems to work only when I actually add a due date value in the due date field (manual entry, not automatically calculated).