Hi all,
I've checked all previous answers to this question but it didn't help.
We have an issue in Ready for UAT status and underneath it 2 sub-tasks(both of status Done).
When clicking complete sprint, appears the message
Complete Sprint: Sprint A2RAP 10May-21May 2021
Sprint cannot be completed as there are incomplete subtasks on the following issues:
Although the 2 subtasks ore of status Done.
1- The board filter query filters on issues of type Story, Epic
2- When adding the Done column as the last column, the issue is not solved
When checking the board filter query to also include subtasks this does not solve the issue
Please advise
Best Regards,
Shaimaa