Do all Closed issues count towards velocity on a Version Report?
I'm looking at a Version Report for my team's next release. I'm seeing the predicted release date on the Version Report is a month and a half earlier than my manual calculations.
I also see that Story Points on Completed Issues on the Version Report is 134 points higher than what I manually calculated that we actually worked on.
I suspect that this is due to some issues that are status "Closed" but that we didn't actually work on. We Closed them as Resolution: Duplicate or Resolution: Won't Fix.
Can you confirm that these issues are counting towards the velocity on the Version Report?
If so, what's a workaround for this? Should we create a status other than Closed so they don't get counted on the Version Report?
Thank you!