Go to Agile - Planning Board. Choose a project and context
scenario 1 : Ensure "Hide Done Issues" tab is not selected. Capacity line is drawn after Issue A.
Scenario 2 : Now click "Hide Done Issues". Capacity line marker moves down and draws after Issue C.
Whether you hide or show done issues, i would expect capacity line to be drawn after the same story
Is the current behaviour of "Hide Done Issues" altering capacity expected?
We're running Jira 4.4.4 with Greenhopper 5.8.7