I am fairly new to BigPicture.
I created a bunch of JIRA Tasks and arranged them using BigPicture Gantt chart according to my Planned Start/Finish Dates (01/08/2021).
So when I complete such tasks and enter the Actual Start/Finish Date (01/29/2021) along with the logged hours (which for whatever reason it is not the same as the Planned one). I would expect to see that change in the Gantt, but no, I still see the Task in the same original date.
Is it possible to automatically have the tasks updated in the Gantt with the Actual Start/Finish Date once I have completed and updated the Task using JIRA? I really need to now if this is possible since we need to know how the completion date will affect the overall planning and timing for linked Tasks