I am in jira project "OELZ" and want to assign some epics, but the list also shows me a lot more epics from project "AF", which are done and which I don't want to see here:
according to the post here, this issue should be solved
[JSWSERVER-12016] The "Epic Link" field list Epics from all the projects instead of the current one - Create and track feature requests for Atlassian products.
Hi @Alexander Pappert
Unfortunately, with reference to the given ticket, atlassian did not restrict the epics scope to a project but only fine tunes the list better with suggestions and filtering out done issues.
See https://jira.atlassian.com/browse/JSWSERVER-12016?focusedCommentId=820661&page=com.atlassian.jira.plugin.system.issuetabpanels%3Acomment-tabpanel#comment-820661
And about the 'done epics', it doesnt refer to the status or resolution. Epics have a special field called 'epic status'. When that value is set to 'done', then the epic is considered as done.
Yes @Alexander Pappert
go to the backlog and "Mark as Done" the epics what are in DONE status or configure an automation to "Mark as Done" alone when the epic is transitioned to DONE.
Best regards.