The goal is to create an automation that when run creates a Task with Subtasks.
To try & achieve this, I've created a very simple automation task configured as follows:
Create a new issue in:
Project: Test
Issue type: Task
Summary: task test
+
Create a new issue in:
Project: Test
Issue type: Subtask
Parent Issue: Current issue
Summary: subtask test
However when run, it shows the below output including an error at the subtask step:
Action details:
Create issue
Issues created successfully
TEST-32
Create issue
Error creating issue
Issue type is a sub-task but parent issue key or id not specified. (issuetype)
Please advise what the problem is here?
Thanks