Hello,
I'm trying to setup an automation that will copy values from Target Start and Target End to a linked issue. I have the automation set up and can get the cloned issue updating, but I am having trouble with the Target Start / End fields that are created by Advanced Roadmaps.
I have the 'Edit issue' action running on linked issues, and am using the Additional Fields to set these values. If I use the following, the dates are copied but are one day behind the trigger issue.
{
"fields": {
"Target start": "{{triggerissue.Target start}}",
"Target end": "{{triggerissue.Target end}}"
}
}If I try to work around this by using .plusdays(1) (as in below) then I get 'Error parsing date string'.
{
"fields": {
"Target start": "{{triggerissue.Target start.plusDays(1)}}",
"Target end": "{{triggerissue.Target end.plusDays(1)}}"
}
}Where am I going wrong here?