I am preparing for ACP 600 and came across this question -
All projects use a simplified workflow which has three statuses (Open, In Progress, Closed) and all global transitions.
You need to find issues which were never In Progress. Select the correct JQL query.
A. Status WAS Open OR Status WAS Closed B. Status != “In Progress”
C. Status NOT Changed TO “In Progress”
D. Status WAS NOT “In Progress”
E. Status ONLY IN (Open, Closed)
what should be the correct answer to this?
Shouldn't it be D?