Hi
I have a calendar with a 5 day work week. There are public holidays. But we have working days sometimes on Saturdays or Sundays. How to add a working day?
Hi @Sergei
Welcome to the Community!
Unfortunately, you're not able to add a working day to the calendar. If you work some Saturdays and Sundays you would need to have a 7 day calendar and add holidays for the weekends you're not working.
Hope that helps,
Regards, Liam
This is terrible. Out of 52 Saturdays, I only need 3
thanks for the answer
I agree it isn't ideal - I'd suggest opening a feature request with Atlassian to see if it is something they would look to do in thee future.
Feel free to accept my answer if it has answered your query.
It looks like you're new here. Sign in or register to get started.