Hello,
we have one "old" (O) server with JIRA 7.2.3, which is Oracle-based. Due to needed OS upgrade, we decided to setup a "new" (N) JIRA-system now using SQL Server.
On N we installed 7.2.3, imported configuration of O and upgraded to 8.13. This went well.
Currently our developer still work with O and we cannot set this system offline during working hours.
Our plan is now to run a backup on O and import it on N. However when trying it, we again see the configuration items of O in N, which is unwanted.
So how to proceed without the same efforts (meaning: without needing to upgrade N again from 7.2.3 to 8.13) more simplified?
Is this possible?
Thanks in advance.