Is there a way to see velocity for completed sprints, if I update the SP(Story point) for the issues after they have been closed in the corresponding(closed) sprint?
Granted that, SPs are to be entered before sprint starts and it is not encouraged to change the SP(Story point) during and after Sprint. But if team has introduced new basis of estimate and would like to see historically how team would have performed if this basis was estimate had been in place, this would be good to know.
Note: I understand we can simply edit SP value in any Jira issue after it is closed. But the updates do not get reflected in the Velocity report ( since the sprint is closed). Any work around?