Dear community,
We have a workflow for defects which can in short be described as
Analysis -> Development -> Acceptance Test -> Resolved.
The development team are working using JIRA sprints, but their responsibility ends when development (and module testing) is done, where the defect is handed over to the Acceptance Test Team, to be tested once the release is shipped (once every 3-4 sprints or so).
Now to the problem. The Development team can not close the sprint in JIRA properly, as the JIRA Defect issue is completed from their point of view, but it is not yet Resolved in JIRA, as it has to pass all the states in the Acceptance test phase of the workflow.
Do you know of a suitable way around this? Today they move these issues into the next sprint, although all the work needed by the development team is already done.
Kind regards