Hi All,
I Have scenario where:
- First, in a very initial stage i'm giving an estimation on the epic level in time units of weeks
- Then, on the story level, in the release planning i'm estimating the stories in time units of days
- Finally in the sprint planning a detailed estimation in hours
So now i'm having an issue, if i'm giving an original est. on both stories and their Sub-tasks the estimated field on the story level is updated to the sum of the story+sus-tasks estimation.
I would like to maintain the org. est. of the story and see kind of a correct est. for the sum taken from the sub-tasks(And off course, all should be aggregated to the Epic level as well).
So currently to achieve that i'm not updating estimates on the sub-tasks level, only using Time tracking. But i'm afraid this will affect me as i'm using the OOB reports like the burndown and velocity charts.
Any advise?
Thanks
Shirley