I have a Version with several Epics and within each Epic there may/may not be Stories. The % complete for the Epics are 0% which in turn shows 0% for the Version. However, when I change the status of one Epic to "In Dev", the Version is showing 14% complete. I understand it's because there seems to be some work happening. What I can't figure out is when I turn the status of the Epic back to "To Do", the Version still shows as 14% complete. Why?
I'll also mention we are using the Server version of JIRA and it is integrated with Aha.