In addition to large projects and backend work, my team receives a large amount of quick content changes for our website. The expectation is that these can be done in less than 20 minutes and we have a dedicated developer that makes these changes. Sometimes these are made and approved before EOB the same day.
We are currently discussing the best practices for dealing with these type of tickets in Jira. Our main thought is we cannot put these into normal sprint planning because the expectation across our org is that these are very quick changes and should not take weeks to get to. Waiting until the next sprint is even too long. The different options discussed are as follows:
- Creating an always open sprint that these can live in and using versions to align the due date with the end of the sprint current sprint.
- Leaving them in the backlog to be completed and including manual search filters to include that developer's work in sprint and EOQ reporting.
- Continually add those tickets to the current sprint and complete are they are done.
Are there any best practices around fast and easy tickets in Jira and in Agile?