We use Tempo Timesheets in the live environment of our JIRA and we are trying out Tempo Planner in our test environment since we expected to fix our obstacle this way...
In our process, we handle a lot of projects or initiatives at any given moment in time.
Therefore a planned Issue does not give us the insight in which project the effort is planned.
Can I adjust this view so that it shows which Project or Initiative this Issue belongs to?
The overview in Teams: Timesheets does have the option to show the Project, Epic and Issue level, so does the Tempo: Reports section.
All in all, my end-goal is to be able to compare hours planned and hours spent on all our different projects. Does our projection match our execution.
I hope this is possible.
A CS representative at Tempo replied to me that this is not a feature available in Tempo.
She advised me to submit a feature request in their 'Ideas' section.
In the meantime, does anyone here have a possible solution available?