I'm trying to determine how scope change % is calculated in the Sprint Health Gadget in Jira. On one of sprints, my team started with 120 points and added two 5 point & and one 3 point stories and it says the scope change is 125%...this has to be incorrect.
I confirmed in my board configuration I'm using Story Points and not issue count for the estimation method.
Any insight would be greatly appreciated!