Hi,
I have setup a project automation rule for the following scenario.
A New User Service request that creates 5 subtasks when the parent issue transitions to the assigned status.
So at this point we have the parent as assigned and the 5 subtasks start with the assigned status also. (perfect! - both sr and subtask have separate workflows...)
The automation (project) that i have setup transitions the parent issue to "work in progress" status, when one of the 5 subtasks move to work in progress".
This works, but i'm getting the following errors...
Action details:
This rule was configured with a project restriction. You can change this restriction in the 'Rule details' section. Only issues from the following projects or project types will be considered:MESD
Related issues condition
The following issues passed:MESD-89
Transition issue
Destination status could not be resolved. If using a smart-value ensure this resolves to a numeric status ID or untranslated name for issues (with current status):MESD-89 (Work In Progress - 10089)
Associated items:
Issue event
Branch rule / related issue
Also, what doesnt work, is if i put all subtasks back to a "assigned" status, it doesnt move the parent back to assigned.
The rules that i have setup are:

Can anyone offer some direction here. Thanks