What is the best solution for this case:
There is a Story that has 8 Story Points and 5 sub-tasks. Sprint is finished but only 3 sub-tasks are completed.
Because of that we can't consider Story finished. How can we count how many Story Points were done during this sprint? 3/5*8? or 0?
second question:
When this story is moved to the next sprint would you leave completed tasks as complete in new sprint or delete them? Would you reduce Story Points (8) for this story (because 3 sub-tasks are already done)