When setting a holiday on Big Picture Holiday Plans, when it's saved, the day moves to the left, hence one day earlier. Once you save the calendar, sometimes all days move an additional day to the left. Now it's 2 days off. Sometimes the dates show as correct on the left under Floating Holiday. But once it's saved again, the dates again move to the left.
We're unable to figure this out. Cannot find any settings although to the left of < 2020 > under Edit details there is what looks like a cog. When you hover over it, you get a hand but other than that, it does nothing.
We've checked documentation but no answers. Is anyone else having this issue? We're using version 7.5, Jira server v. 8.3.x on a closed network.