Can I get a burndown / progress report of sub tasks within issues?
Hello @jmacfarlane
Welcome to Atlassian Community!
Unfortunately, the Jira burndown report does not consider sub-task estimation, not counting it towards the completion of related Sprints. That being said, we understand the value of this functionality and created the following feature request to get it implemented:
- Burndown chart doesn't take under consideration the sub-tasks estimation
Feel free to vote and watch the suggestion to increase its priority and also receive notifications about any updates.
As a workaround, you can sum the estimation of your sub-tasks to its parent issue, using the burndown chart to display the parent estimation.
Let us know if you have any questions.
Excellent!
It looks like you're new here. Sign in or register to get started.