When completing a sprint, stats display for "Done", "Incomplete" and "Partially Complete" statuses. What is the difference between "Incomplete" and "Partially Complete"?
Olive
Accepted answers
Petar Petrov _Appfire_
Partially complete issues are issues which have subtasks, where some of the subtasks were completed during the sprint.
Incomplete issues are the issues that are not done,
minus
any partially completed issues.
All comments
Petar Petrov _Appfire_
Partially complete issues are issues which have subtasks, where some of the subtasks were completed during the sprint.
Incomplete issues are the issues that are not done,
minus
any partially completed issues.
Olive
Thank you!! Makes perfect sense!