Hi there,
We are having troubles with schedulling in portfolio in the older version. We are currently working in KANBA.
Problem:
Epics aren't next to each other, but are under. The reason is, that system is filling small tasks (stories, issues) in developers capacity.
The question:
How can tell the system not to fill the small gaps and instead of that concentrate all of the developers time on one epic and start another epic after the previous is finished.
Here is how it looks like in epic view:
Thank you for all you advices 