Hi,
I have a follow-up question according to this discussion: https://answers.atlassian.com/questions/28328/jira-and-sub-tasks
There is this answer from Nic Brough:
"...
If you want to get the report to say 2 hours, you need to make the estimate for the top-level issue 2 hours. Your options here are
- Remove the 2 hour estimate from the top level issue
- Remove the estimates from the subtasks
- Move the subtasks out, as they're not supposed to be included
"
Now my question is, what is the most convenient way to achieve point 1 automatically with JIRA/Greenhopper?
Little explanation of the usage scenario:
At the beginning Stories are created and roughly estimated. At some point in the future maybe Subtask are created for that Story to specify the work to be done in more detail. These Subtask get their own estimates, but most likely these estimates were part of the orginal estimate of the Story. Hence the latter one needs to be reduced accordingly. And it would be fine to get this done automatically.