I cannot find a place to tell Portfolio what workdays to use or what holidays to use. Perhaps I am attempting to use the program incorrectly?
In Jira Server 8.3.0 I have a Kanban to gather tasks across multiple projects. The Kanban board has configured working days (M-F) and excludes some company holidays. The issues contain estimated durations in weeks. The start and end dates are empty.
I've used the Kanban board as a basis for a new plan in Portfolio. When auto schedule runs it counts weekends and holidays as working days. So an 8 wk ( 40 working days) task from the issue estimate becomes a (roughly) 30 working day task on Portfolio's Roadmap.
Is that just how it works, or am I doing something wrong? Does anyone have a favorite work around for this?
Thank you