Trying to help a user that has an active sprint combined of stories, blockers, sub-task & releases from two projects. His board filter is:
project = project A OR project = Project B ORDER BY Rank ASC
There were originally issues w/his work flow statuses and board columns but we've resolved those. I've verified the columns are correct with To Do, In Progress & Done. All of the the Done issues have a resolution of Done. However, Work Completed on the Sprint Health Gadget shows "0%". If I run a query that says sprint = ### & resolution = Done, 23 issues pull up.