Scenario: During sprint planing you pull in 5 stories into the sprint. You break each story into a subtasks. You are estimating using "original time estimate". You then start the sprint. A few days goes by and the dev team realizes they for got to add a sub task to one of the stories.
Question: Would the subtask be considered adding scope?
My thoughts:
1. If you pull up the sprint report only "issues" how up with an asterisk, so no it wouldn't add scope.
2. It wouldn't add scope because if you add a subtask to a story and put time against the sub task Jira does not aggregate the time into the story.
Thoughts?