What is Estimated Time Remaining calculated based on? The documentation does not include this information. Is this just av field the user writes in, or is it automatically calculated, if so how is the calculating?
Documentation: https://confluence.atlassian.com/jira064/time-tracking-report-720416014.html
This is calculated based on "Original Estimate" and "Time Spent".
If you had 2d as Original Estimate, and if you have logged .5d and .5d twice for this issue, Time Spent will 1d and Estimated Time Remaining will be 1d.
So it will always be Orginal Estimate - Time spent = Estimated time remaining?
Is it possible to send a mail when Estimated time remaining is passing 10 hours forexample?
Yes.
You can look at `Filter Subscriptions` for this.
Look at this page `Receiving Results via EMail` section - https://confluence.atlassian.com/jiracoreserver073/working-with-search-results-861257284.html
For creating filter for `Estimated Time Remaining` you can use following JQL.
remainingEstimate > 10h
thanks:) But this would not work if there are more than 200 tasks in the list, and the recipiant should be the worker on the task?
@SlaekkeYou can look for plugin in marketplace for this.
I mostly use Subscriptions for these kind of workflow.
You can try `ScriptRunner` this can be done in it with very simple script.
Also, writing a small plugin for some custom workflow is always a possibility in Jira.
It looks like you're new here. Sign in or register to get started.