If in a Transition of sub task can use the post fuction "Create / Clone issue(s) (JMWE add-on)" to create a sub task
My understanding of that function is that it can either
Point 3 cannot work here, because you cannot have a sub-task of a sub-task, and there's nowhere to tell the post-function which parent issue to use (unless maybe it assumes the parent of the current sub-task? I've not tested that)
Hi Ya - Welcome to the Atlassian Community!
Yes, you can create a Clone of a Sub-task. Both would be linked to the same parent.
I hope that helps!
I got it. Thanks for your answer
Hi Ya - Great! If that works for you can you click on the Accept answer button to close this one out?