Hi,
I'm trying to understand why one of our burndown charts appears to be including the points on Stories that are in the Done column on the sprint board.
We have 22 points in the To Do column, 43 in the In Progress and 30 in the Done Column, but rather than display 65 left in the Burndown it shows 95, which seems too coincidental to be adding up to 30 from anywhere else.
Looking at the sprint report shows stories coming in, some sizing done in the sprint, some stories taken out of the sprint, some completed to Done, some closed. All this is reflected in the Inc and Dec columns.
I'm curious to know what the query is that drives the Burndown Chart to ascertain where the values are coming from.
Many thanks in advance for any help.
Cheers
Colin