I have a portfolio project created where it gives me the view of an EPIC (Feature) and the linked Stories under that need to fulfill the EPIC. This shows me my roadmap based off my estimates. I have run into an issue in how bugs are also included in this plan.
Background:
EpicE (feature)
- StoryA (6 hours from the total sub-tasks)
--Subtask A1 - 2hrs
--Subtask A2 - 4hrs
If a BUG is raised by the team, they will create a bug, then associate this bug to the EPIC and then create the relevant subtasks to fulfill this BUG
- BugB (10 hours from the total sub-tasks)
--Subtask B1 - 5hrs
--Subtask B2 - 5hrs
In my plan EpicE currently says it will be finished in 6 hours time (StoryA only). when in fact i want to say 16 hours time it will be completed (StoryA plus BugB).
How do i get bus to show in my plan like stories do