1. Project includes stages
2. Stages include tasks (they have different default estimates)
3. Each stage starts when the previous stage has been completed only (means all entire tasks are completed)
4. If any task goes over due - stage misses deadline and shifts all roadmap for this delay time
5. Save the template of this project with stages and tasks
Project Structure:
1. Project
2. Stages (maybe Epics)
3. Tasks
Stage includes tasks and has deadlineTask has estimate
It means thatStage Printing is time bounded: jul.14.2019 - jul.24.2019 (10 days)
Task 1 is load paper 1 day
Task 2 is print 3 days
Task 3 is get prints 2 days
Task 4 is delivery 5 days
if Task 3 takes more than 2 days (eg 5 days) - Stage Printing endtime becomes jul.27.2019