I currently have in my schema estimation in user points
Is it possible to modify it to estimation in days?
Hello,
You should add the timetracking field to the screens, which are linked to the issues, where you want to track estimation in days.
Hi,
Time tracking is about logging time, while I'm looking for estimation phase, so it can be further used for the sprint planning etcÂ
Open the board, which you use, go to the Board Settings -> Estimation and choose Original Time Estimate.
is this available also in kanban board? can't find it there
It looks like you're new here. Sign in or register to get started.