Parent assignment has subtasks. Subtasks can either be Approved or Rejected. How can I make it so the parent task can be closed ONLY if ANY 1 subtask is approved?
******************************************Approve is a workflow status
Conditions must be set in the workflow to allow the outcome of what you want with your subtasks.
Hope the link will be helpful
https://confluence.atlassian.com/jirakb/preventing-issues-from-being-closed-while-their-sub-task-are-still-open-724928276.html
The condition is actually called "Sub-Task Blocking Condition" if that helps at all.
Thank you, yes I see this blocking condition. However, I can only find the option to close the parent task if ALL the subtasks are Approved. I want to ability to have engineers submit subtasks from a parent, my team Approve or Reject, and only when 1 subtask is Approved will the parent close.
Is approve a workflow status or a custom field?