Is it possible to use the runner script to do this?
I need to calculate how many days (day of the week) I need to work to consume all the estimated hours.
Example:
Estimate = 200h
Resource = 2 dev
Time dedicated 4h per day
Start of activity 2/23/2017
200 (estimated hours) / 4 (hours per day) = 50 (days)
50 (days) / 2 (dev resources) = 25 working days
Starting the activity on 2/23/2017, how to add 25 days? (These days being only days of the week (ignoring weekends))
How many days do I have to work to consume these hours?
25 days
What day will I finish work?
I do not know (how to add 25 days only day of week from 02/23/2017?)